As innovation has become an essential business activity, it faces much more scrutiny from investors and boards, and the pressure to justify its return keeps growing. In our webinar What Makes a New Technology Investable? A Live Model Demo, Lux Chief Product Officer Dr. Arij van Berkel and Senior Director and Principal Analyst Anthony Schiavo explained why the standard capital investment toolkit is the wrong test for innovation, and walked through a live model demo of a better one, using a plastic pyrolysis project as the case.
Key takeaways
- Deterministic NPV is the wrong test, applied too early. It’s built for a known asset, so it rejects the ideas with the most to gain from development.
- An innovation is an option to develop. It buys the right to build later while capping the downside at the development cost, and uncertainty is the source of its value.
- The endpoint is a set of targets, not a verdict. Real options analysis tells you how much development budget a project justifies and what has to improve to make it investable.
Why innovation needs a different model
Back in 2018, Lux looked at Volkswagen’s innovation investments over time. R&D intensity (R&D expenditure divided by gross revenue) rose from about 3.5% to close to 6%, while capital intensity declined with trends like outsourced production and just-in-time delivery. For many companies, R&D intensity and capital intensity are now pretty similar, which puts innovation squarely in focus for investors and board meetings.
The natural reflex is to judge innovation the same way as capital expenditure, with net present value and internal rate of return. Lux’s view is that this doesn’t work, because an investment in innovation doesn’t generate a cash flow. It creates the opportunity to invest in a capital asset later. And when you evaluate a project before further development, it will fail the test. The projects most likely to be rejected are the ones that could make the biggest advancements through development.
An innovation is an option to develop
Instead, investing in innovation is like buying an option:
- It buys the right to build later. A development program commits the company to nothing but the development budget. The capital decision comes later, when technology and market are clearer.
- The downside is capped. If the project turns out worse than hoped at any milestone, you can opt out and lose the development cost, not the capital.
- Uncertainty is the source of its value. Uncertainty means the outcome could be worse than you thought, but it also means it could be better.
With a financial call option, market events such as quarterly results, competitor news or a product launch change the value before the decision date. In an R&D project, every milestone (performance targets, validation tests, pilot economics) is a bifurcation in value, and you have far more control over those events. Market events, like new regulation or a competitor’s project being delayed or accelerated, play a role too.
The live demo: a plastic pyrolysis project
Arij then walked through Lux’s internal suite of models, which runs from a deterministic techno-economic model to a Monte Carlo simulation, a real options calculation, a risk hurdle rate model and an optimization model for innovation planning. The case was a plastic pyrolysis plant taken from Lux’s research on making plastic recycling scalable: about 17,000 tons per year of pyrolysis oil from 25 kilotons of plastic waste at 65% conversion, the reference being a project planned in the Netherlands.
Deterministic model. At $580 per ton, the 10-year average price of naphtha, and a 12% weighted average cost of capital, the verdict was clear: don’t invest. The internal rate of return came out at −100% and the net present value at −$111 million, because the levelized cost needed for a 12% return is about $1,460 per ton. Even with a premium for recycled content that lifts the price to about $1,200 per ton, the project only works for someone willing to accept roughly a 5% return.
Monte Carlo simulation. Next came uncertainty: a 40% spread around the $1,200 price, plus uncertainty in capital expenditure (it’s a first-of-a-kind), operational expenditure (driven by electricity and plastic feedstock prices) and production uptime. The expected internal rate of return rose to 7.65%, 80% of combinations produced a viable business case, and returns ranged from −8.1% at the 5th percentile to 22.7% at the 95th.
Real options. Using the Black-Scholes equation, the option value of the project came out at $16.2 million, which you can treat as a rough development budget. A word of caution: scaling the plant up four times raised the option value to $78 million, but it also implicitly committed the company to spending almost $240 million after the project and to capturing 2.3% of the market instead of 0.6%. The option value depends on how much skin in the game you’re willing to have.
Risk hurdle rate. Because the value comes from uncertainty, the project is riskier than an average business activity. The risk hurdle rate model put the return you should want at 27% instead of 12%.
Optimization. Finally, the optimization model varied capital expenditure, operational expenditure and production to find what it would take to make the project viable: reduce capital expenditure by 8.4%, reduce operational expenditure by 17.9% and increase production by 20.7%, which brings the expected internal rate of return to 17.1%. Those become concrete assignments: cheaper plastic or electricity for the trading team, and a higher yield (from 65% to 68 or 69%) and better unit reliability for the research group.
How to put the framework to use
- Start before the case looks good. A weak base case is the entry point, not the exit.
- Value the option, not just the business case. Judge an innovation by the right to invest later under a capped downside, and by the development budget it justifies.
- Separate the development decision from the deployment decision. Real options decides whether development is worth funding; investment hurdles decide whether deployment justifies the capital.
- Let your own risk appetite set the hurdle. The return an innovation must earn depends on the company that will deploy it.
- Turn the analysis into targets. What to improve, by how much, and the budget that justifies it.
- Rerun it at every gate, and read it across the portfolio. Costs fall and uncertainty narrows as a program matures.
Q&A highlights
Q: How does this apply to working with or investing in a startup?
A (Arij van Berkel): It’s not fundamentally different. The option value can be regarded as the valuation of the startup. If the option is worth about $16 million and you invest $4 million, you should expect about 25% of the shares. The pricing of a startup may be very different, but it gives you a ballpark, and if you end up paying $40 million for 25%, you’d have some questions.
Q: What pushback should you expect from a CFO or CEO?
A (Arij van Berkel): The real pushback is garbage in, garbage out. Competent engineers will reverse engineer the numbers, but that’s fine, because the model lets you see which assumptions they had to make to make the project investable. If those assumptions are ultra-optimistic, you know what risk you’re taking. It’s much more a risk management tool than an economic modeling tool.
Watch the full webinar
Watch What Makes a New Technology Investable? A Live Model Demo on demand to see the full model demo. Have a project of your own? Bring your project data and we’ll run it through the model with you. Email [email protected].